Client: Gardiner & Theobald LLP  on behalf of westonbirt school

Project Overview:

Client: Gardiner & Theobald LLP  on behalf of westonbirt school

Location: westonbirt School Tetbury Gloucestershire

Project Manager: Neil Bishop

Site Manager: Jake Simpson

Duration: 12 weeks

Project Overview: The F10 notified project was to carry asbestos removal & disposal.  Demolish the music & Gym building in very tight restraints.

Scope of Works:

Demolition & site clearance

Asbestos Removal.

Designed scaffolding around Gym building.